Planning risk
Planning permission can be the greatest risk on a construction project.
Deciding whether to make an outline or detailed application, and when to make an application is of great importance. Typically clients wish to secure planning permission as soon as possible so as to minimise abortive design costs. However, being granted planning permission may become more likely as the design develops and more details can be provided to the planning authority.
On design and build projects delays in obtaining planning permission (which the contractor has taken reasonable steps to avoid) may be grounds for an extension of time, and loss and / or expense and may become grounds for termination of the contract if the delay results inthe works being suspended.
On private finance initiative projects, the client should at least consult the local planning authority to establish the likely planning parameters for the project and perhaps seek a screening opinion as to whether an environmental impact assessment will be required before seeking bids. The client may also wish to obtain outline planning permission before seeking bids, or even to make the contract conditional upon detailed planning permission being received. The contractor (integrated supply team) may then be responsible for obtaining detailed planning permission or any further permissions, for which purpose the contractor acts as agent of the client. Failure to obtain detailed planning permission may result in termination of the contract, giving rise to compensation events.
Problems can be caused by misunderstandings, misinterpretations, incomplete applications, applications that are not in an appropriate form, payment of fees, the timing of planning committee meetings and so on. To ensure that there are no delays, it is wise to seek pre-application advice from the local planning authority who can clarify the form of the application required and the information that it may require. If it is necessary for the application to be determined by the local planning committee (rather than by planning officers under delegated authority) they will be able to advise about the timing of meetings and whether the applicant might make representations to the committee.
Planning performance agreements can be prepared for complex applications, or applications where the statutory timescale is likely to be exceeded. These are voluntary undertakings that enable local planning authorities and applicants for planning permission to agree the timescales, actions and resources necessary to process a planning application. They are not intended to be legally-binding contracts, but are in the spirit of a ‘memorandum of understanding’.
Featured articles and news
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.
The changed R&D tax landscape for Architects
Specialist gives a recap on tax changes for Research and Development, via the ACA newsletter.
Structured product data as a competitive advantage
NBS explain why accessible product data that works across digital systems is key.
Welsh retrofit workforce assessment
Welsh Government report confirms Wales faces major electrical skills shortage, warns ECA.
A now architectural practice looks back at its concept project for a sustainable oceanic settlement 25 years on.
Copyright and Artificial Intelligence
Government report and back track on copyright opt out for AI training but no clear preferred alternative as yet.
Embedding AI tools into architectural education
Beyond the render: LMU share how student led research is shaping the future of visualisation workflows.
Why document control still fails UK construction projects
A Chartered Quantity Surveyor explains what needs to change and how.
Inspiration for a new 2026 wave of Irish construction professionals.
New planning reforms and Warm Homes Bill
Take centre stage at UK Construction Week London.